Task
Expansion of a municipal wastewater treatment plant to include a 2-stage, biologically activated filtration plant (BAF) with flushing equipment and optimization of the existing pre-treatment stage and sludge treatment. The modular biofiltration plant comprises the stages of chemical phosphorus precipitation, upstream denitrification and nitrification (each with integrated residual phosphorus elimination).
Design data
Preparation quantity:
- Daily wastewater volume: 18,000 m³/d
- Population equivalent: 60,000 PE
Target parameters:
- Treated wastewater in accordance with EU water legislation requirements for discharge
Solution & implementation
Our main focus in this task was on reducing pollutant loads, particularly with regard to chemical oxygen demand (COD), biochemical oxygen demand (BOD5), filterable substances as well as nitrogen and phosphorus compounds. We successfully mastered this challenge by optimizing the mechanical pre-treatment and using a modular biofiltration system.
Our two-stage biologically activated filtration unit(ALMA BHU BAF) includes a preparatory step for phosphorus removal using iron(III) chloride and flocculants(wastewater chemistry from ALMAWATECH).
Through the integrated denitrification and nitrification processes, we effectively reduce COD, nitrogen compounds and the remaining phosphorus compounds. Biofiltration is carried out in an upflow process and uses inorganic filter materials for optimum results.
References municipal wastewater treatment
Slovenia
biological treatment
ALMA BHU BAF
Similar projects
Biogas plant for Keszthely sewage treatment plant, Hungary, ALMA BHU GMR
Construction of a biogas plant for the sludge utilization of a municipal sewage treatment plant with an energy production of 2,000 kWh/d in Hungary.
Focsani wastewater treatment plant, Romania, wastewater treatment and biogas plant
Turnkey construction of a municipal wastewater treatment plant with biogas plant as sludge treatment for a total wastewater volume of 40,000 m³/d in Romania.
Alba lulia wastewater treatment plant, Romania, wastewater treatment and biogas plant
Construction of a municipal wastewater treatment plant with biological phosphorus elimination and a biogas plant for a total wastewater volume of 21,562 m³/d in Romania.
Velenje municipal utilities, Slovenia, ALMA BHU BAF, BIO
Expansion of a municipal wastewater treatment plant with reduction of nitrogen and phosphorus compounds and biofiltration for a total wastewater volume of 18,000 m³/d in Slovenia.
SC AQUABIS S.A, Romania, biological phosphorus elimination, denitrification
Expansion of four municipal wastewater treatment plants for a total wastewater volume of 1,440 m³/h with a focus on nitrogen and phosphorus degradation using biological processes in Romania.
Tecuci wastewater treatment plant, Romania, pre-treatment, biological treatment, post-treatment, sludge treatment
A municipal wastewater treatment plant for a wastewater volume of 14,177 m³/d with mechanical pre-treatment, biological treatment, post-treatment and sludge treatment in Romania.
Guangda Water Management, China, ALMA BHU LHPS, BAF, Ozone
A municipal wastewater treatment plant for a wastewater volume of 12,000 m³/d with precipitation/flocculation reactors, biologically activated filtration and ozonation in China.
Weihai wastewater treatment plant, China, ALMA BHU LHPS, BAF, pre-treatment, sludge treatment
A municipal wastewater treatment plant for a wastewater volume of 40,000 m³/d and a population equivalent of 166,667 in China.