Task
Badische Stahlwerke has been a major manufacturer of high-quality steel products based in Kehl for more than five decades. Their extensive product portfolio includes reinforcing steel in bar and ring form, wire rod, continuous cast billets and reinforcement products. With a dedicated workforce of over 850 employees, they achieve an annual production capacity of an impressive 2,000,000 tons of their first-class steel products.
In 2022, ALMAWTECH was awarded the contract to pre-treat the wastewater from slag processing in order to relieve the existing sand filters. This strategic decision underlines Badische Stahlwerke's efforts to minimize its environmental impact while optimizing its production processes.
Design data
The wastewater to be treated is characterized by a considerable proportion of solids and an extremely high metal and oil content. The wastewater plant is intended to relieve the existing sand filtration system.
- Waste water volume: max. 1 - 2 m³/week
Target parameters:
- pH value 6.0 - 9.0
- Solid-free
Solution & implementation
In order to efficiently tackle the challenge of treating small but highly fluctuating volumes of wastewater, we decided to implement a compact CP system with a belt filter for sludge dewatering - the ALMA CP Compact. This innovative solution is complemented by a precise powder dosing station that ensures exact dosing.
Our solid combination product, consisting of precipitation, flocculation, neutralization and reaction release agents, is called ALMA FLOC MWP. These high-quality chemicals are tailor-made to effectively meet the specific requirements of your wastewater treatment.
References Metal Processing & Metallurgy
Similar projects
Similar projects
Möller Medical GmbH, Germany, ALMA CHEM MCW Modular
Treatment of 12m3 of acidic and metal-containing wastewater from electroplating, mass finishing and electropolishing, installed in a two-storey ALMA module for the medical technology manufacturer Möller Medical GmbH.
3M, Germany, ALMA OSMO Process
Construction of a multi-stage pilot membrane plant for the removal of per- and polyfluorinated chemicals (PFAS) from wastewater with a hydraulic capacity of 1 m³/h for the company 3M.
Kalle Casings GmbH & Co. KG, Germany, ALMA CHEM MCW Modular
Treatment of 10m3 of rinsing and production wastewater per day using a precipitation and flocculation system in batch operation for Kalle Casings GmbH & Co. KG, installed in the special ALMA module.
NBG Fiber GmbH, Austria, ALMA CHEM MCW
Treatment of 7.2m3 of laboratory wastewater per day using a precipitation and flocculation plant in batch operation for NBG Fiber GmbH.
Badische Stahlwerke GmbH, Germany, ALMA CP Compact
A compact CP system with powder dosing station and belt filter for sludge dewatering (ALMA CP Compact) for slag wastewater from Badische Stahlwerke in Kehl.
RHM Rohstoff-Handels GmbH, Germany, ALMA NeoDAF Blue
A compact dissolved air flotation system (ALMA NeoDAF Blue 300) with gravel and activated carbon filter for rainwater from chip and scrap metal storage areas at RHM Rohstoff-Handels GmbH.
BRAZETEC GmbH, ALMA Chem MCW
A CP batch plant (ALMA CHEM MCW) with gravel filtration for the new plant of BRAZETEC (formerly SAXONIA Technical Materials GmbH).